Demolition and Construction of Telephone House site, Royal Tunbridge Wells
CALA HOMES' Revised Scheme of Works [1st scheme was refused 9 September 2002]
SCHEME OF WORKS FOR THE DEVELOPMENT OF THE TELEPHONE HOUSE SITE
ROYAL TUNBRIDGE WELLS
BY CALA HOMES (SOUTH) LIMITED
9th OCTOBER 2002
CONTENTS
List of appendices
List of Tables
Introduction
List of Appendices:
Appendix 1 - Plant and Equipment
Appendix 2 - Anticipated material and distribution for Phase 2 - Construction and Phase 3 - Internal Fit-Out and Landscaping.
Appendix 3 - Development Phase Site Layouts
List of Tables
Strategic Programme.
INTRODUCTION
CALA Homes (South) Limited has prepared this document to assist in the understanding of the proposed construction methodology and sequencing of the redevelopment of Telephone House to provide 43 apartments with basement level parking, as required under Condition 15 of Appeal decision APP/M2270/A/00/105496.
Phase 1 - Site Set-up and Demolition - 18 weeks
Principal Contractor: Woolridge Ecotec Limited
Start on site - Event
Site set-up - 2 weeks
Erect Scaffold - 2 weeks
Secure Site Boundary/Signage - 2 weeks
Internal Strip Out - 2 weeks
Hard Demolition - 16 weeks
Clear Site - Event
Phase 2 - Construction
Phase 2/1- Basement/Foundations - 31 weeks
Principal Contractor: CALA Homes (South) Limited
Start on Site - Event
Site Accommodation - 2 weeks
Earth Works 1 - 8 weeks
Earth Works 2 & 3 - 11 weeks
Temp Works No. 27 (4) - 2 weeks
Basement/Foundations Drainage - 23 weeks
Phase 2/2 - Ground Floor Slab - 20 weeks
Ground Floor Slab - 20 weeks
Construction Office/Site Set Up - 3 weeks
Remove Cabins - 1 week
Phase 2/3 - Superstructure - 62 weeks
Superstructure - 40 weeks
Roof Construction - 46 weeks
Strike Scaffold - 46 weeks
Phase 3 - Internal Fit-Out and Landscaping - 49 weeks
Principal Contractor: CALA Homes (South) Limited
Internal Fit Out - 49 weeks
Roof Plant & Penthouse Fit-out Block A1 - 10 weeks
Hard Landscaping - 12 weeks
Soft Landscaping - 5 weeks
Handover/Occupation - 15 weeks
Site Set Up - Duration 2 weeks
Demolition - Duration 16 weeks
Dust control during site set up
Plant and equipment
Site Staff/Visitors
Deliveries
Removal of demolition debris
Basement/Foundations Drainage
KEY ACTIVITIES: Ground Floor Slab
KEY ACTIVITIES:
Superstructure
Roof Construction
Plant Equipment, excavation material
Site Staff/Visitors
Deliveries
Basement Construction
Plant and Equipment
Site Staff/Visitors
Deliveries
Site Staff/Visitors
Deliveries
Site Workers/Visitor
Deliveries
Progressive fit-out of internal blocks
Completion and Landscaping
Handover and occupation of Block Al, A2, B,C,D
Plant and Equipment
Site Workers/Visitors
Deliveries
Skip Movements
![]() |
Impact on York Road - Material Deliveries and Distribution
The Telephone House Neighbours Association analysed and filtered CALA Homes' spreadsheet |
HISTORY
Demolition and Construction of Telephone House site, Royal Tunbridge Wells
CALA Homes' Preliminary Scheme of Works, March 2002, was not submitted to Tunbridge Wells Borough Council
CALA Homes' Scheme of Works (1st) was refused 9 September 2002
CALA Homes' Scheme of Works (2nd) was refused 25 November 2002
CALA Homes' Scheme of Works (3rd) was approved 24 December 2002
![]() | CALA Homes Revised - THIRD Scheme of Works for the Demolition and Construction of Telephone House |
![]() | Is CALA Homes really going ahead with THAT scheme? |