(3rd) SCHEME OF WORKS FOR THE DEVELOPMENT OF THE TELEPHONE HOUSE SITE
HISTORY - Demolition and Construction of Telephone House site, Royal Tunbridge Wells
CALA Homes' Preliminary Scheme of Works including Health and Safety Plan, Method Statement and Risk Assessment, March 2002, was not submitted to TWBC
CALA Homes' Scheme of Works (1st) was refused 9 September 2002
CALA Homes' Scheme of Works (2nd) was refused 25 November 2002
THIS IS THE WARRANTED SCHEME OF WORKS, APPROVED BY TUNBRIDGE WELLS BOROUGH COUNCIL ON 24 December 2002
EXECUTIVE SUMMARY
Demolition Site Set up.
Demolition ( 1 )
Construction & Excavation Phase ( 2 )
Noise
Plant & Equipment used during Demolition Phase
Additional equipment (over and above that already used during demo phase) to be used during construction and excavation phase is
n. 18m2 rigid 8 wheel lorries - various
o. Luffing jib crane,
p. Mobile Crane
Plant & Equipment used during Construction & Excavation Phase
Plant and Equipment used during Internal Fit out and Landscaping Stage
Phase 1 - Site Set-up and Demolition - 14 weeks total
(Principal Contractor: Woolridge Ecotec Limited) -
Start on site - Event
Site set-up & fencing - 2 weeks
Demolition - 12 weeks
Clear Site via Church Road - Event
Phase 2 - Construction
Install Access Ramp through Block A from Church Road & CALA site set up - 2 weeks
Construct Block D
Construct Block B
Construct Block C
Construct Block A
weeks - for all four blocks refer to construction programme 15/11/02
Phase 3 - Internal Fit out and Landscaping
Block D internal fit out - 17 weeks
Block B internal fit out - 24 weeks
Block C internal fit out - 24 weeks
Block A internal fit out - 27 weeks
Landscaping will be completed within the above timescales and in line with the approved landscaping plan.